33kV pole dressing on the SOTTA diversion

SOTTA 33kV overhead line diversion

A new 1,007.8m corridor constructed and transferred while managing the safe removal of the existing line.

June 2025Mining InfrastructureNyanzaga

Project Overview

Re-routing live infrastructure around site development

KELM constructed a new 33kV overhead line to divert supply away from an existing corridor affected by infrastructure development. The assignment required precise route surveying, new line construction, switching coordination, demolition and restoration.

The new route was completed, tested and integrated before the previous poles, conductors and hardware were safely removed.

Client
SOTTA Mining Corporation
Programme
Started and completed June 2025
Location
Nyanzaga, Tanzania
Route Length
1,007.8m of 33kV overhead line
Key Constraint
Transition from the existing route while maintaining supply continuity

What KELM Did

Controlled every stage of the diversion

New Route Design

Surveyed and set out the diversion corridor to clear planned infrastructure works.

Line Construction

Installed poles, insulators, crossarms and conductors with controlled sagging and tensioning.

Supply Transfer

Planned switching and temporary arrangements to manage continuity during cutover.

Demolition & Handover

Removed the old line, restored the site and completed testing and as-built documentation.